Indian Railways focused on several long pending overdue maintenance works which required traffic block of long durations. These works were pending for several years and were confronting Railways with severe bottlenecks. They were planned during lockdown period wipe out these maintenance arrears and take up the execution of work without affecting the train service.
These works taken up for removal of bottlenecks and enhance safety include 82 rebuilding/rehabilitation of bridge, 48 limited height subway/road under bridge in lieu of level crossing gate, 16 construction/strengthening of foot over bridge, 14 dismantling of old foot over bridge, 7 launching of road over bridge, 5 yard remodelling, 1 commissioning of doubling & electrification and 26 other projects.
Some of these key projects are as follows –
Yard modification work in Jolarpetti (Chennai Division, Southern Railway) was completed on 21st May 2020. It resulted in easing out of curve and enhancing the speed up to 60Kmph on Bengaluru end and facilitated Simultaneous reception and dispatch.
Dismantling of old abandoned Foot Over Bridge at Ludhinana (Firozepur Division, Northern Railway) was completed on 5th May 2020. Dismantling of this 135 meter long old abandoned FOB structure over 19 tracks and 7 passenger platforms was overdue since 2014 after new FOB was commissioned.